68 329
Assignments Done
98,8%
Successfully Done
In November 2018

Answer to Question #61018 in C++ for suganya r

Question #61018
TCS is working on a new project called "TestVita". There are N modules in the project. Each module (i) has completion time denoted in number of hours (Hi) and may depend on other modules. If Module x depends on Module y then one needs to complete y before x.

As Project manager, you are asked to deliver the project as early as possible.
Provide an estimation of amount of time required to complete the project.
Expert's answer

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be first!

Leave a comment

Ask Your question

Submit
Privacy policy Terms and Conditions