The construction of a building may be delayed by a strike. Suppose that the
probability that there will be a strike is 0.70, the probability that the construction
will be completed on time if there is no strike is 0.90 and the probability that the
building will be completed on time if there is a strike is 0.40, what is the
probability that the construction will be completed on time.
1
Expert's answer
2017-08-22T12:27:07-0400
Let the event “there will be a strike” is A, the event “the construction will be completed on time” is B.
P(A)=0.7
P(B|A ̅ )=0.9
P(B|A)=0.4
P(B)=P(A)P(B|A)+P(A ̅ )P(B|A ̅ )=P(A)P(B|A)+(1-P(A))P(B|A ̅ )
P(B)=(0.7)0.4+(1-0.7)0.9= 0.55
Answer: 0.55.

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS