Answer to Question #42730 in Math for sparsh

Question #42730
A and B together can complete a piece of work in 15 days. A alone undertakes the work. He works for 18 days and leaves the job. Then B alone undertakes the remaining work and completes it in another 10 days. Had A continued the work, how many more days he would have required to complete the work alone?

A 8 days

B 6 days

C 9 days

D 12 days
1
Expert's answer
2014-05-23T06:57:51-0400
The answer to the question is available in the PDF file https://www.assignmentexpert.com/https://www.assignmentexpert.com/homework-answers/mathematics-answer-42730.pdf