Question #31303
it takes 1 work day to repair 100m of road.
At this rate,about how many work days will it take to repair 20 km of road?
1
Expert's answer
2013-05-28T10:44:56-0400
The person can repair 100m of road during 1 work day.
Let's convert kilometers into meters: 20km = 20 000meters.
If the person each day will repair 100 meters, then 20000 meters he/she can repair in 20 000 / 100 = 200 work days