Explain each parameter in the sequencing model: n/m/F/Fmax
1
Expert's answer
2019-04-17T09:10:23-0400

This simple notation written as n/m/F/Fmax means flow shop scheduling: to minimize the maximum makespan or flow time with m machines and n jobs.

n is used to denote a number of job-arrival processes;

m means the number of machines in the given scheduling problem;

F is used in flow shop scheduling, or the flow pattern of jobs through machines used in the shop;

Fmax refers to the criterion for determining a schedule of jobs.