Answer to Question #178956 in Algebra for Nicole

Question #178956

3. The formula below is often used by projection manager to computer E the estimated time to complete a job, where is the shortest completion time, P is the longest completion time and M is the most likely completion time. E = (0 + 4M + P)/6 Which of the following correctly gives in terms of E ; , and M? a. P = 6E - O - 4M b. P = - 6E + O + 4M


1
Expert's answer
2021-04-15T06:34:07-0400
"E=(O+4M+P)\/6"

Then


"P=6E-O-4M"



a. "P=6E-O-4M"



Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
APPROVED BY CLIENTS