1. Can you guarantee that a feasible schedule exists without a simulation of the schedule or time demand analysis, if
(a) The set of tasks T = {(5, 2),(8, 3),(10, 1)} is scheduled by the rate-monotonic algorithm.
(b) The set of tasks T = {(3, 1),(6, 1),(18, 6),(36, 4)} is scheduled by the least-slack-time-first algorithm.
(c) The set of tasks T = {(3, 1),(0, 6, 1, 4),(18, 6),(36, 4)} is scheduled by the earliest-deadline-first algorithm.
(d) The set of tasks T = {(3, 1),(6, 1),(18, 6),(36, 4)} is scheduled by the deadline-monotonic algorithm
The answer to the question is available in the PDF file https://www.assignmentexpert.com/https://www.assignmentexpert.com/homework-answers/engineering-answer-53423.pdf
Numbers and figures are an essential part of our world, necessary for almost everything we do every day. As important…
APPROVED BY CLIENTS
Finding a professional expert in "partial differential equations" in the advanced level is difficult.
You can find this expert in "Assignmentexpert.com" with confidence.
Exceptional experts! I appreciate your help. God bless you!
Comments
Leave a comment