Answer to Question #87350 in Finance for sahil

Question #87350
You are at the midpoint of a project and have used only 30% of your budget. Does this mean that you will be under budget at the end of the project? Explain your answer.
1
Expert's answer
2019-04-05T10:02:35-0400

It is not a fact that we will finish the project under budget.


At first, it depends on the terms of spendings. If we expect the biggest payments in the final stage of a project (like purchasing of equiplment or buildings), we can run out of budget.


Secondly, the meeting of budget depends on exchange rate and the settled currency of project plan. If currency rate changes, we can overrun costs.


Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS