3. A project has 11 activities: Activity-A to Activity-K.

a. Prepare a network diagram and list different chains of activities. Use the following 

information.

Activity No: A B C D E F G H I J K

Predecessor     A B B D D C F,G E H,I,J

b. Compute the project duration and identify critical path. Use the following additional 

information.

Activity  A B C D E F G H I J K

Duration 2 3 3 7 8 3 5 10 4 6 3 


1
Expert's answer
2021-05-25T21:27:02-0400

a) START>A >B> B> D> D> C >F>G> E> H>I>J>END

b) 2 3 3 7 8 3 5 10 4 6 3  =4684 0