Question #129626
B. Exercise on Earned value Information:
• The annual budget of the project is Birr 150000
• Budgeted Cost of Work Schedule (BCWS) for the work at the end of the sixth month is 75000
• Work completed at the end of the sixth month= 45%
• Actual cost incurred in the sixth months = 85000
Required Calculate:
a. The schedule variance: - BCWP-BCWS 45000-75000= -30000
b. The cost variance: - BCWP-ACWP 45000-85000= -40000
c. Schedule performance index: - BCWP/BCWS 45000/75000= 0.6
d. Cost performance index:- BCWP/ACWP 45000/85000= 0.53
e. Comment on the progress of the project and explain what remedial measures should management take in the remaining six months of the project to be on the track.
1
Expert's answer
2020-08-14T02:50:24-0400
Dear eyobtilahun, your question requires a lot of work, which neither of our experts is ready to perform for free. We advise you to convert it to a fully qualified order and we will try to help you. Please click the link below to proceed: Submit order

Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS