Answer to Question #201523 in Mechanical Engineering for Saurav Swaraj

Question #201523

a research and development department is developing a new power supply for a console television set. it has broken the job down into the following

a) Determine the network diagram of activities involved in the project and indicate the 

critical path

b) What is the minimum completion time for the project?


1
Expert's answer
2021-06-02T07:43:23-0400

1) In project management, the critical path is the longest sequence of tasks that must be completed to successfully conclude a project, from start to finish. The tasks on the critical path are known as critical activities because if they're delayed, the whole project will be delayed.

2) The shortest time a project can be completed is called the minimum completion time.




Need a fast expert's response?

Submit order

and get a quick answer at the best price

for any assignment or question with DETAILED EXPLANATIONS!

Comments

No comments. Be the first!

Leave a comment

LATEST TUTORIALS
New on Blog
APPROVED BY CLIENTS